Nippert Stadium Hardhat Wednesday: March 18, 2015

facebooktwitterreddit

As we sit on the eve of the two greatest days of the sports year (the first round of March Madness), it’s time for another Nippert Stadium Hardhat Wednesday.  I happened to be on campus last week, so I decided to add a few pictures of my own to the latest tri-weekly edition.

  • Railings, stairs, and glass are going in on the exterior – the new West Concourse is really starting to look like a stadium.
  • The skybridge from TUC to the new structure is nearly complete.  The glass wall in the bookstore is currently blocked by drywall, and will soon be replaced by glass doors.
  • Interior walls of the suites are going in, and a mock-up of the cabinetry gives an idea of what the finished suites will look like.
  • East side concession and restroom work is progressing nicely.  The bridges from the East Upper Deck to Sheakley Lawn will be the last thing to go in this Summer.
  • The press area in the new structure will vastly increase space for the media when Nippert reopens with a three-tiered media level.

Here is the video: